Greensboro Housing Authority v. Kirkpatrick & Associates, Inc.
Court of Appeals of North Carolina
1Opinion of the Court
WHICHARD, Judge.
The court based its involuntary dismissal on conclusions that (1) no breach of contract occurred, and (2) if any breach occurred, it could have been discovered by plaintiff in the exercise of reasonable diligence. Its findings of fact, which are supported by competent evidence, sustain its conclusions. We therefore affirm.
The essential facts are:
Plaintiff contracted with Kirkpatrick for the construction of a housing project according to plans and specifications provided by plaintiff’s architects. Kirkpatrick subcontracted the electrical construction to Talley.
Plaintiff…
2Cases cited6 opinions
- SNML Corp. v. Bank of North Carolina, N.A.Court of Appeals of North Carolina · 1979
- Burke County Public Schools Board of Education v. Juno Construction Corp.Court of Appeals of North Carolina · 1981
- McNeely v. SOUTHERN RAILWAY COMPANYCourt of Appeals of North Carolina · 1973
- Burke County Public Schools Board of Education v. Juno Construction Corp.Supreme Court of North Carolina · 1981
- Ward v. Thompson Heights Swimming Club, Inc.Court of Appeals of North Carolina · 1975
1 more not listed; retrieve them via the Exa API.
3Cited by7 opinions
- Olympic Products Co. v. Roof Systems, Inc.Court of Appeals of North Carolina · 1988
- William L. Thorp Revocable Trust v. Ameritas Investment Corp.District Court, E.D. North Carolina · 2014
- Design Plus Store Fixtures, Inc. v. Citro Corp.Court of Appeals of North Carolina · 1998
- Sexton v. United StatesDistrict Court, E.D. North Carolina · 1991
- Blue Cross and Blue Shield v. WR Grace & Co.District Court, D. South Carolina · 1991
2 more not listed; retrieve them via the Exa API.