F. M. Sibley Lumber Co. v. Wayne Circuit Judge
Michigan Supreme Court
1Opinion of the CourtFellows, J.
Dickinson Land Company agreed to build for Kate Weiss a two-family flat for $13,500, a part of that sum to be made up of an equity in a land contract and the balance in cash. She has paid $8,000 in cash. Plaintiff lumber company furnished some of the material and has filed a claim of lien for the sum of $3,523.48. Kate Weiss claims the house did not comply with the contract. September 16, 1925, the lumber company filed its bill to foreclose its lien; it made the Dickinson Land Company, Kate Weiss, and others defendants. Kate Weiss filed a cross-bill setting up the breach of the contract and…
2Cases cited17 opinions
- McLaughlin v. AustinMichigan Supreme Court · 1895
- Kirkwood v. HoxieMichigan Supreme Court · 1893
- West v. FlemmingIllinois Supreme Court · 1857
- Peninsular General Electric Co. v. NorrisMichigan Supreme Court · 1894
- People ex rel. Granger v. Judge of the Wayne Circuit CourtMichigan Supreme Court · 1873
12 more not listed; retrieve them via the Exa API.
3Cited by13 opinions
- Ronnisch Construction Group, Inc v. Lofts on the Nine, LLCMichigan Supreme Court · 2016
- Abner A. Wolf, Inc. v. WalchMichigan Supreme Court · 1971
- Roseliep v. HerroWisconsin Supreme Court · 1931
- Canvasser Custom Builders, Inc. v. SeskinMichigan Court of Appeals · 1972
- Farwell v. NealMichigan Court of Appeals · 1972
8 more not listed; retrieve them via the Exa API.