Supreme Court of North Carolina
1Opinion of the CourtDeviN, J.
An examination of the complaint would seem to justify defendants’ demurrer ore tenus interposed in the court below and in this *365Court, for it is nowhere alleged that at the time the notice of material-man’s claim was given defendants there was anything due the contractor. The remedies by statutory liens, authorized by sections 2437, 2438, 2440, and 2442 of the Consolidated Statutes, under which plaintiffs’ lien was filed and this action brought, are available only “before the owner shall have paid the contractor.” Rose v. Davis, 188 N. C., 355, 124 S. E., 576.
While upon the question whether at…