OPINION
BJORKMAN, Judge.
Appellant insurance company challenges the district court’s denial of summary judgment to appellant and grant of summary judgment to respondent subcontractor on respondent’s payment-bond claim. Because service of the notice of claim was defective, we reverse.
FACTS
The City of Owatonna hired Niles-Wiese Construction Company as the general con-. tractor for the construction of an airport runway and taxiway. Pursuant to Minn. Stat. § 574.26, subd. 2(2) (2010), Niles-Wiese obtained a payment bond from appellant Westfield Insurance Company. The payment bond — a contract…
2Cases cited14 opinions
- Star Centers, Inc. v. Faegre & Benson, L.L.P.Supreme Court of Minnesota · 2002
- Eischen Cabinet Co. v. HildebrandtSupreme Court of Minnesota · 2004
- In Re StadsvoldSupreme Court of Minnesota · 2008
- Ceco Steel Products Corp. v. TapagerSupreme Court of Minnesota · 1940
- Wheeler Lumber Bridge & Supply Co. v. Seaboard Surety Co.Supreme Court of Minnesota · 1944
9 more not listed; retrieve them via the Exa API.
3Cited by1 opinion
- Safety Signs, LLC v. Niles-Wiese Construction Co.Supreme Court of Minnesota · 2013