Safety Signs, LLC v. Niles-Wiese Construction Co.
Supreme Court of Minnesota
1Opinion of the Court
OPINION
WRIGHT, Justice.
The principal dispute in this case is whether a subcontractor gave proper notice of a payment-bond claim under Minn. Stat. § 574.31, subd. 2(a) (2012). Appellant Safety Signs, LLC, was a subcontractor on a public project. Safety Signs brought suit against general contractor Niles-Wiese Construction Company and respondent-surety Westfield Insurance Company, seeking to recover money owed under the subcontract. It is undisputed that Niles-Wiese defaulted. But Westfield moved for summary judgment on the payment-bond claim because Safety Signs mailed its pre-suit notice of…
2Cases cited16 opinions
- Valspar Refinish, Inc. v. Gaylord's, Inc.Supreme Court of Minnesota · 2009
- In Re the Civil Commitment of GiemSupreme Court of Minnesota · 2007
- Sullivan v. Credit River TownshipSupreme Court of Minnesota · 1974
- Cretex Companies, Inc. v. Construction Leaders, Inc.Supreme Court of Minnesota · 1984
- Ruiz v. 1st Fidelity Loan Servicing, LLCSupreme Court of Minnesota · 2013
11 more not listed; retrieve them via the Exa API.
3Cited by3 opinions
- Steven J. Jaeger v. Palladium Holdings, LLC, Franklin Financial, LLCSupreme Court of Minnesota · 2016
- Keith Feder, M.D., Inc. v. U.S. BancorpDistrict Court, D. Minnesota · 2025
- Keith Feder, M.D., Inc. v. U.S. BancorpDistrict Court, D. Minnesota · 2025