Rutter v. McLaughlin
Idaho Supreme Court
1Opinion of the Court
BAKES, Justice.
Plaintiff appellant Ralph F. Rutter agreed, for a specified price, to construct a house for defendant respondents James D. McLaughlin and Willa K. McLaughlin. Rutter and the McLaughlins entered into a written construction contract using a standard form agreement drafted by the American Institute of Architects (AIA). The standard form AIA contract utilized by the parties was designed to allow incorporation of a number of other documents and provided, in Article 16, for enumeration of any additional documents intended to be incorporated into the contract. When a dispute arose…
2Cases cited8 opinions
- Werry v. Phillips Petroleum CompanyIdaho Supreme Court · 1975
- Cullison v. City of PeoriaArizona Supreme Court · 1978
- Dawson v. MeadIdaho Supreme Court · 1976
- Glenn Dick Equipment Co. v. Galey Construction, Inc.Idaho Supreme Court · 1975
- Stewart v. Arrington Construction CompanyIdaho Supreme Court · 1968
3 more not listed; retrieve them via the Exa API.
3Cited by86 opinions
- Shawver v. Huckleberry Estates, L.L.C.Idaho Supreme Court · 2004
- Moss v. Mid-American Fire & Marine InsuranceIdaho Supreme Court · 1982
- Farmers National Bank v. ShireyIdaho Supreme Court · 1994
- Opportunity, L.L.C. v. OssewardeIdaho Supreme Court · 2002
- DeLancey v. DeLanceyIdaho Supreme Court · 1986
81 more not listed; retrieve them via the Exa API.