This case concerns the effect of a provision in a construction contract that conditions payment upon a municipal official’s certificate of performance. The plaintiffs, Frank Grenier, John Grenier and Eugene Grenier, brought an action against the defendant, Compratt Construction Company, to recover $25,500 which the defendant had agreed to pay for blasting work performed in the construction of certain roads. The defendants responded with an answer and a counterclaim seeking to enforce a liquidated damages clause in the contract. After a trial to the court, judgment was rendered for the…

2Cases cited13 opinions

  1. Brauer v. FrecciaSupreme Court of Connecticut · 1970
  2. Kakalik v. BernardoSupreme Court of Connecticut · 1981
  3. Strimiska v. YatesSupreme Court of Connecticut · 1969
  4. Ravitch v. Stollman Poultry Farms, Inc.Supreme Court of Connecticut · 1973
  5. Hebert v. DeweyMassachusetts Supreme Judicial Court · 1906

8 more not listed; retrieve them via the Exa API.

3Cited by17 opinions

  1. Magnan v. Anaconda Industries, Inc.Supreme Court of Connecticut · 1984
  2. Aetna Casualty & Surety Co. v. MurphySupreme Court of Connecticut · 1988
  3. Blakeslee Arpaia Chapman, Inc. v. EI Constructors, Inc.Supreme Court of Connecticut · 1997
  4. Dills v. Town of EnfieldSupreme Court of Connecticut · 1989
  5. West Haven Sound Development Corp. v. City of West HavenSupreme Court of Connecticut · 1986

12 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API