Graham Construction Co. v. Robert H. Pyle, Inc.
Court of Appeals of Texas
1Opinion of the Court
OPINION ON MOTION FOR REHEARING
NYE, Justice.
After careful consideration of appellants’ motion for rehearing, we withdraw our opinion delivered in this cause and substitute therefor the following opinion.
This is a suit for debt due on a written contract brought by appellee Robert H. Pyle, Inc. against Graham Construction Company, the general contractor and National Surety Corporation. This case and Cause Number 278, Graham Construction Company et al. v. Walker Process Equipment, Inc. 1 were consolidated for the purposes of trial before the court sitting without a jury. However, each suit was…
2Cases cited7 opinions
- New Amsterdam Casualty Co. v. Texas Industries, Inc.Texas Supreme Court · 1967
- Wagner v. RiskeTexas Supreme Court · 1944
- Golden State Mutual Life Insurance Co. v. AdamsCourt of Appeals of Texas · 1960
- Graham Construction Co. v. Walker Process Equipment, Inc.Court of Appeals of Texas · 1967
- Janes v. MortonCourt of Appeals of Texas · 1964
2 more not listed; retrieve them via the Exa API.
3Cited by13 opinions
- Sage Street Associates v. Northdale Construction Co.Texas Supreme Court · 1993
- Lanphier Construction Co. v. Fowco Construction Co.Court of Appeals of Texas · 1975
- Augusta Development Co. v. Fish Oil Well Servicing Co., Texas Court of Appeals, 13th District1988
- Goren v. GorenCourt of Appeals of Texas · 1975
- BPR Construction & Engineering, Inc. v. RiversCourt of Appeals of Texas · 1980
8 more not listed; retrieve them via the Exa API.