Legal Opinion

Town of Norwood, Massachusetts v. Federal Energy Regulatory Commission, Yankee Atomic Electric Company, Intervenor

Court of Appeals for the D.C. Circuit

Decided April 9, 1996No. 94-1710PublishedCited by 9 opinions

1Opinion of the Court

Opinion for the Court filed by Circuit Judge TATEL.

TATEL, Circuit Judge:

After Yankee Atomic Electric Company shut down a nuclear power plant before the plant’s license expired, the Federal Energy Regulatory Commission allowed Yankee to recover from ratepayers 100% of its remaining unamortized investment, construction-work-in-progress, decommissioning costs, and the operating expenses of the closed plant. To reflect the plant shutdown, the Commission also reduced Yankee’s rate of return. The Town of Norwood, one of Yankee’s ratepayers, now seeks review of the Commission’s order. In view of…

2Cases cited5 opinions

  1. Federal Power Commission v. Hope Natural Gas Co.Supreme Court of the United States · 1944
  2. Democratic Central Committee of the District of Columbia v. Washington Metropolitan Area Transit Commission, D. C. Transit System, Inc., IntervenorCourt of Appeals for the D.C. Circuit · 1973
  3. Jersey Central Power & Light Company v. Federal Energy Regulatory Commission, Allegheny Electric Cooperative, Inc., IntervenorsCourt of Appeals for the D.C. Circuit · 1987
  4. Illinois Cities of Bethany v. Federal Energy Regulatory Commission, Central Illinois Public Service Co., IntervenorCourt of Appeals for the D.C. Circuit · 1981
  5. Nepco Municipal Rate Committee and the Electric Departments and Plants of Ashburnham v. Federal Energy Regulatory Commission, New England Power Company, Dennis J. Roberts, Ii, Attorney General of Rhode Island, Intervenors. New England Power Company v. Federal Energy Regulatory Commission, Dennis J. Roberts, Ii, Attorney General of Rhode Island, Nepco Municipal Rate Committee, Intervenors. New England Power Company v. Federal Energy Regulatory Commission, Nepco Municipal Rate Committee, Massachusetts Department of Public Utilities, Fitchburg Gas and Electric Light Co., Intervenors. New England Power Company v. Federal Energy Regulatory Commission, Nepco Municipal Rate Committee, Intervenors. New England Power Company v. Federal Energy Regulatory Commission, Dennis J. Roberts, Ii, Attorney General of Rhode Island, IntervenorsCourt of Appeals for the D.C. Circuit · 1981

3Cited by9 opinions

  1. Maine v. Federal Energy Regulatory CommissionCourt of Appeals for the D.C. Circuit · 2017
  2. Yankee Atomic Electric Co. v. United StatesUnited States Court of Federal Claims · 2006
  3. ENGIE Gas & LNG LLC v. Department of Public UtilitiesMassachusetts Supreme Judicial Court · 2016
  4. Sierra Club v. FERCCourt of Appeals for the D.C. Circuit · 2022
  5. LA Pub Svc Cmsn v. FERCCourt of Appeals for the D.C. Circuit · 1999

4 more not listed; retrieve them via the Exa API.