Maine v. Federal Energy Regulatory Commission
Court of Appeals for the D.C. Circuit
1Opinion of the Court
SENTELLE, Senior Circuit Judge:
Under the Federal Power Act (“FPA”), the Federal Energy Regulatory Commission (“FERC” or “the Commission”) must ensure that all rates charged for the transmission or sale of electric energy are “just and reasonable.” 16 U.S.C. §§ 824d(a), 824e(a). Petitioners New England Transmission Owners (“Transmission Owners”) provide transmission services for customers in New England. In 2011, Petitioners Massachusetts and various consumer-side stakeholders (“Customers”) filed a complaint under section 206 of the FPA, 16 U.S.C. § 824e, alleging that Transmission Owners’…
2Cases cited39 opinions
- Motor Vehicle Mfrs. Assn. of United States, Inc. v. State Farm Mut. Automobile Ins. Co.Supreme Court of the United States · 1983
- Federal Power Commission v. Hope Natural Gas Co.Supreme Court of the United States · 1944
- Permian Basin Area Rate CasesSupreme Court of the United States · 1968
- Montana-Dakota Utilities Co. v. Northwestern Public Service Co.Supreme Court of the United States · 1951
- Federal Power Commission v. Natural Gas Pipeline Co.Supreme Court of the United States · 1942
34 more not listed; retrieve them via the Exa API.
3Cited by41 opinions
- Kansas Corp. Commission v. Federal Energy Regulatory CommissionCourt of Appeals for the D.C. Circuit · 2018
- New England Power Generators Ass'n v. Federal Energy Regulatiory CommissionCourt of Appeals for the D.C. Circuit · 2018
- Verso Corp. v. Fed. Energy Regulatory Comm'nCourt of Appeals for the D.C. Circuit · 2018
- In re: NTE Connecticut, LLCCourt of Appeals for the D.C. Circuit · 2022
- Ameren Services Co. v. Federal Energy Regulatory CommissionCourt of Appeals for the D.C. Circuit · 2018
36 more not listed; retrieve them via the Exa API.