Chameleon Integrated Services, Inc. v. United States
United States Court of Federal Claims
1Opinion of the Court
Bid protest; Federal Acquisition Streamlining Act; task order contract; STARS II GWAC.
OPINION
BRUGGINK, Judge.
This is a post-award bid protest. It involves a challenge by plaintiff, Chameleon Integrated Services, Inc. (“Chameleon”), to the award by the United States Department
of Agriculture (“USDA”) of a task order to intervenor, CSSS.net (“CSSS”), under a preexisting government-wide acquisition contract (“GWAC”), STARS II. 2 Plaintiff alleges in its motion for judgment on the administrative record that the award to CSSS was unreasonable, among other reasons, because CSSS received an unfair…
2Cases cited9 opinions
- Axiom Resource Management, Inc. v. United StatesCourt of Appeals for the Federal Circuit · 2009
- A & D Fire Protection, Inc. v. United StatesUnited States Court of Federal Claims · 2006
- Vanguard Recovery Assistance v. United StatesUnited States Court of Federal Claims · 2011
- DGS Contract Service, Inc. v. United StatesUnited States Court of Federal Claims · 1999
- Idea International, Inc. v. United StatesUnited States Court of Federal Claims · 2006
4 more not listed; retrieve them via the Exa API.
3Cited by3 opinions
- Sra International, Inc. v. United StatesUnited States Court of Federal Claims · 2014
- Pricewaterhousecoopers Public Sector, LLP v. United StatesUnited States Court of Federal Claims · 2016
- Guam Industrial Services, Inc. v. United StatesUnited States Court of Federal Claims · 2015