Massman Construction Co. v. Lake Lotawana Ass'n
Missouri Court of Appeals
1Opinion of the CourtBland, J.
This is an action for the balance claimed to be due under-an excavation contract. There was a verdict and judgment in favor of plaintiff in the sum of $8521.56, and in favor of defendant in the sum of $700 on its counterclaim based upon plaintiff’s delay in performing the work. Defendant appealed to the Supreme Court and that court transferred the cause here.
The facts show that on July 14, 1944 the parties hereto entered into a written contract in which plaintiff undertook to make certain improvements to the spillway in the dam at Lake Lotawana in Jackson County, consisting of .the…
2Cases cited18 opinions
- Williams v. Chicago, Santa Fe & California Railway Co.Supreme Court of Missouri · 1892
- Myers v. Union Electric Light & Power Co.Supreme Court of Missouri · 1933
- Chapman v. Kansas City, Clinton & Springfield Railway Co.Supreme Court of Missouri · 1898
- Chapman v. Kansas City, Clinton & Springfield RailroadSupreme Court of Missouri · 1893
- Bowen v. LazalereSupreme Court of Missouri · 1869
13 more not listed; retrieve them via the Exa API.
3Cited by17 opinions
- Terminal Construction Corp. v. Bergen County Hackensack River Sanitary Sewer District AuthoritySupreme Court of New Jersey · 1955
- Weitz Co. v. MH WASHINGTONCourt of Appeals for the Eighth Circuit · 2011
- Southwest Engineering Co. v. Reorganized School District R-9Missouri Court of Appeals · 1968
- New Pueblo Const., Inc. v. LAKE PATAGONIA REC. ASSOCIATION, INC.Court of Appeals of Arizona · 1970
- Sides Construction Co. v. Arcadia Valley R-II School DistrictMissouri Court of Appeals · 1978