Bushman Construction Co. v. United States
United States Court of Claims
1Opinion of the CourtWhitaker, Judge
This case is before us on defendant’s motion for summary judgment.
Plaintiff sues under a contract with the Department of the Interior for the increased wages it was required to pay on account of a redetermination of the prevailing wage made by the Secretary of Labor after the execution of the contract between the parties. Under the contract plaintiff was to perform certain work dealing with the earthwork and structures on the Missouri River Basin Project.
*266Plaintiff says the Davis-Bacon Act (40 U. S. C. 276a) required only that a Government contract should provide that the contractor should…
2Cases cited1 opinion
- United States v. Binghamton Construction Co.Supreme Court of the United States · 1954
3Cited by5 opinions
- Grade-Way Construction v. United StatesUnited States Court of Claims · 1985
- Cipparulo v. David Friedland Painting Co.New Jersey Superior Court Appellate Division · 1976
- Morrison-Hardeman-Perini-Leavell v. The United StatesUnited States Court of Claims · 1968
- Twin Falls Construction Co. v. Operating Engineers Local 370Idaho Supreme Court · 1973
- Meaott Construction Corp. v. RossAppellate Division of the Supreme Court of the State of New York · 1980