United States Fidelity & Guaranty Co. v. Ed Hockaday & Co.
Supreme Court of Oklahoma
1Opinion of the CourtDavison, J.
The Green Construction Company entered into a contract with the board of county commissioners of Custer county whereby it contracted to build and make a certain public improvement, the construction of the South Canadian river bridge in said county. The Green Construction Company furnished the statutory bond required, given and underwritten by the plaintiff in error, United States Fidelity & Guaranty Company, conditioned that the Green Construction Company, as contractor, should pay all indebtedness incurred for labor or material furnished in the construction of said bridge.
In the construction…
2Cases cited5 opinions
- Rittenhouse & Embree Co. v. F. E. Brown & Co.Illinois Supreme Court · 1912
- Fuller v. BrooksSupreme Court of Oklahoma · 1926
- W. R. Pickering Lbr. Co. v. FullerSupreme Court of Oklahoma · 1926
- Tway v. ThompsonSupreme Court of Oklahoma · 1932
- Green Construction Co. v. ChornSupreme Court of Oklahoma · 1935
3Cited by4 opinions
- Tom P. McDermott, Inc. v. BennettSupreme Court of Oklahoma · 1964
- Lucas v. Western Casualty & Surety Co.Court of Appeals for the Tenth Circuit · 1949
- CPS Distributors, Inc. v. Federal Insurance Co.Colorado Court of Appeals · 1984
- National Automobile & Casualty Insurance Co. of Los Angeles v. AdairSupreme Court of Oklahoma · 1955