New Mexico Industrial Energy Consumers v. New Mexico Public Service Commission
New Mexico Supreme Court
1Opinion of the Court
OPINION
SOSA, Senior Justice.
This case concerns a decision by the New Mexico Public Service Commission (Commission) to develop a methodology to apply in future rate cases brought by the Public Service Company of New Mexico (PNM) to account for excess generating capacity. Appellant, New Mexico Industrial Energy Consumers (NMIEC), moved to intervene. All of the interested parties agreed to form a Task Force to study the problem and make recommendations to the Commission. The Task Force arrived at a Stipulation, which NMIEC did not sign. The Commission held a hearing and subsequently entered a…
2Cases cited11 opinions
- Mathews v. EldridgeSupreme Court of the United States · 1976
- Logan v. Zimmerman Brush Co.Supreme Court of the United States · 1982
- United States v. Florida East Coast Railway Co.Supreme Court of the United States · 1973
- Matter of ValdezNew Mexico Supreme Court · 1975
- Ernest W. Hahn, Inc. v. County AssessorNew Mexico Court of Appeals · 1975
6 more not listed; retrieve them via the Exa API.
3Cited by19 opinions
- New Mexico Industrial Energy Consumers v. New Mexico Public Regulation CommissionNew Mexico Supreme Court · 2007
- New Mexico Industrial Energy Consumers v. New Mexico Public Service CommissionNew Mexico Supreme Court · 1991
- In Re Com'n InvestigationNew Mexico Supreme Court · 1999
- U S West Communications, Inc. v. New Mexico State Corp. CommissionNew Mexico Supreme Court · 1999
- Behles v. New Mexico Public Service CommissionNew Mexico Supreme Court · 1992