Hellander v. United States
United States Court of Claims
1Opinion of the Court
LARAMORE, Judge.
In this action plaintiff seeks to recover damages in the amount of $66,349.30 allegedly incurred by him in the performance of a contract with the Bureau of Reclamation for the construction of certain earthwork and structures for an irrigation project. His claim is in five counts: (1) as the result of faulty contract specifications, he incurred repair costs in order to build siphons that would not leak. Said repair costs were occasioned by reason of defendant’s use of the irrigation system before it was formally accepted; (2) that upon oral assurance of defendant’s agents that…
2Cases cited4 opinions
- United States v. Blair Ex Rel. Roanoke Marble & Granite Co.Supreme Court of the United States · 1944
- A. L. Coupe Construction Co. v. United StatesUnited States Court of Claims · 1956
- P. J. Carlin Construction Co. v. United StatesUnited States Court of Claims · 1940
- Dunn v. United StatesUnited States Court of Claims · 1943
3Cited by16 opinions
- J. G. Watts Construction Co. v. United StatesUnited States Court of Claims · 1963
- Inland Empire Builders, Inc., J. C. Boespflug Construction Co., and McLaughlin Inc. v. The United StatesUnited States Court of Claims · 1970
- Schutt Construction Co. v. United StatesUnited States Court of Claims · 1965
- Harvey-Whipple, Inc. v. United StatesUnited States Court of Claims · 1965
- Paul v. United StatesUnited States Court of Claims · 1990
11 more not listed; retrieve them via the Exa API.