Willard, Sutherland & Co. v. United States
Supreme Court of the United States
1Opinion of the CourtJustice Butler
This suit was brought to recover $3,650, being $3.65 per ton for 1,000 tons of coal furnished the Navy. Appellant claims that it is entitled to the market price at the time of delivery, $6.50 per ton. The United States claims that appellant was bound by contract to furnish it for $2.85 per ton. The Court of Claims made findings of fact, and concluded that appellant was not entitled to recover.
In the spring of 1916, the Navy Department, being desirous of making contracts for coal for the ensuing fiscal year ending June 30,1917, issued its invitation for bids in the form of a schedule…
2Cases cited15 opinions
- Insurance Co. v. DutcherSupreme Court of the United States · 1877
- Old Colony Trust Co. v. City of OmahaSupreme Court of the United States · 1913
- Cold Blast Transp. Co. v. Kansas City Bolt & Nut Co.Court of Appeals for the Eighth Circuit · 1902
- United States v. Purcell Envelope Co.Supreme Court of the United States · 1919
- Topliff v. TopliffSupreme Court of the United States · 1887
10 more not listed; retrieve them via the Exa API.
3Cited by108 opinions
- Torncello v. United StatesUnited States Court of Claims · 1982
- E. I. Du Pont De Nemours & Co. v. Claiborne-Reno Co.Court of Appeals for the Eighth Circuit · 1933
- Dynamics Corporation of America, as Successor in Interest to International Fermont, Inc. v. The United StatesUnited States Court of Claims · 1968
- Northern Helex Co. v. United StatesUnited States Court of Claims · 1972
- Mason v. United StatesUnited States Court of Claims · 1980
103 more not listed; retrieve them via the Exa API.