Willems Industries, Inc. v. United States
United States Court of Claims
1Opinion of the CourtDueKee, Judge
In this action, plaintiff seeks damages in the amount of $1,800,000 for losses alleged to have been sustained in consequence of breach of contract by defendant and defendant counterclaims for $976,000 damages alleged to have resulted from a breach of contract by the plaintiff.
During September 1950, Jess Larson, Administrator of the General Services Administration (GSA) created the Emergency Procurement Service (EPS) within GSA and delegated to it authority he had received from the Munitions Board to purchase, store, and dispose of critical and strategic materials for the national stockpile…
2Cases cited3 opinions
- Winn-Senter Const. Co. v. United StatesUnited States Court of Claims · 1948
- Holmberg v. United StatesUnited States Court of Claims · 1940
- United States v. US Foreign CorporationDistrict Court, S.D. New York · 1957
3Cited by55 opinions
- Lisbon Contractors, Inc. v. The United StatesCourt of Appeals for the Federal Circuit · 1987
- Mega Construction Co. v. United StatesUnited States Court of Federal Claims · 1993
- G.M. Shupe, Inc. v. United StatesUnited States Court of Claims · 1984
- Morrison Knudsen Corp. v. Fireman's Fund InsuranceCourt of Appeals for the Tenth Circuit · 1999
- Franconia Associates v. United StatesUnited States Court of Federal Claims · 2004
50 more not listed; retrieve them via the Exa API.