Commercial Casualty Insurance v. Durham County
Supreme Court of North Carolina
1Opinion of the CourtYaeseb, J.
The contract provision that 85 per cent of the value of labor and material used during the previous month, as estimated by the architect, shall be paid by the owner to the contractor at the dates specified during the progress of the work creates in the 15 per cent reserve balance an equity in which the surety has a substantial right. "While the owner also has an equity in this reserved balance, he has no right, without the consent of the surety to waive it, or to exceed the provisions of the contract in making payments to the contractor. The retained balance is well calculated to induce the…
2Cases cited14 opinions
- Prairie State Bank v. United StatesSupreme Court of the United States · 1896
- Miller v. StewartSupreme Court of the United States · 1824
- County of Glenn v. JonesCalifornia Supreme Court · 1905
- Graham v. Proctorville WarehouseSupreme Court of North Carolina · 1925
- Guilford Lumber Manufacturing Co. v. HolladaySupreme Court of North Carolina · 1919
9 more not listed; retrieve them via the Exa API.
3Cited by12 opinions
- Brick Co. v. . GentrySupreme Court of North Carolina · 1926
- Ideal Brick Co. v. GentrySupreme Court of North Carolina · 1926
- Wilson v. Commercial Finance Co.Supreme Court of North Carolina · 1954
- Fort Worth Independent School Dist. v. Ætna Casualty & Surety Co.Court of Appeals for the Fifth Circuit · 1931
- National Surety Co. v. County Board of Education of McDowell CountyCourt of Appeals for the Fourth Circuit · 1926
7 more not listed; retrieve them via the Exa API.