West Bay Builders, Inc. v. United States
United States Court of Federal Claims
1Opinion of the Court
OPINION AND ORDER
SWEENEY, Judge.
Before the court are Plaintiffs Motion for Summary Judgment and Defendant’s Cross-Motion for Summary Judgment, both of which were filed pursuant to Rule 56 of the Rules of the United States Court of Federal Claims (“RCFC”). Plaintiff seeks a ruling from the court that defendant, acting through the Department of Veterans Affairs (“VA”) Northern California Health Care System, failed to compensate it for additional contract costs related to the application of concrete floor moisture sealant during renovations to Building 90 of the VA Palo Alto Health Care System,…
2Cases cited83 opinions
- Anderson v. Liberty Lobby, Inc.Supreme Court of the United States · 1986
- Celotex Corp. v. Catrett, Administratrix of the Estate of CatrettSupreme Court of the United States · 1986
- Matsushita Electric Industrial Co., Ltd. v. Zenith Radio CorporationSupreme Court of the United States · 1986
- First Nat. Bank of Ariz. v. Cities Service Co.Supreme Court of the United States · 1968
- United States v. SherwoodSupreme Court of the United States · 1941
78 more not listed; retrieve them via the Exa API.
3Cited by13 opinions
- Oenga v. United StatesUnited States Court of Federal Claims · 2010
- Raytheon Co. v. United StatesUnited States Court of Federal Claims · 2012
- Jay Cashman, Inc. v. United StatesUnited States Court of Federal Claims · 2009
- Premier Office Complex of Parma, LLC v. United StatesUnited States Court of Federal Claims · 2017
- Wyoming Sawmills, Inc. v. United StatesUnited States Court of Federal Claims · 2009
8 more not listed; retrieve them via the Exa API.