Ace Constructors, Inc. v. United States
Court of Appeals for the Federal Circuit
1Opinion of the Court
NEWMAN, Circuit Judge.
ACE Constructors, Inc. entered into a contract with the United States Army Corps of Engineers to build a structure designated the Ammo Hot-Load Facility, at Biggs Army Airfield at Fort Bliss in El Paso, Texas. Several disputes arose and, after a five-day trial, the Court of Federal Claims decided several issues in favor of ACE, awarded an equitable adjustment to ACE in the amount of $1,383,009 with statutory interest, and ordered the return of liquidated delay damages in the amount of $246,130. 1 On this appeal by the United States, we affirm the judgment of the Court of…
2Cases cited12 opinions
- United States v. United States Gypsum Co.Supreme Court of the United States · 1948
- United States v. Winstar Corp.Supreme Court of the United States · 1996
- United States v. SpearinSupreme Court of the United States · 1918
- Mobil Oil Exploration & Producing Southeast, Inc. v. United StatesSupreme Court of the United States · 2000
- Scott Timber Company v. United StatesCourt of Appeals for the Federal Circuit · 2003
7 more not listed; retrieve them via the Exa API.
3Cited by63 opinions
- Linc Government Services, LLC v. United StatesUnited States Court of Federal Claims · 2010
- Eastern Electric Corp. v. Shoemaker Construction Co.District Court, E.D. Pennsylvania · 2009
- Dobyns v. United StatesUnited States Court of Federal Claims · 2010
- System Fuels, Inc. v. United StatesUnited States Court of Federal Claims · 2007
- Redland Co. v. United StatesUnited States Court of Federal Claims · 2011