Legal Opinion · Dissent

Borrelli v. H AND H CONTRACTING, INC.

Connecticut Appellate Court

Decided April 17, 2007No. AC 25905Published

1DissentFlynn, C. J.

I respectfully dissent from the majority opinion. This breach of contract case raises two key questions: (1) whether the plaintiffs were entitled to have the defendant construct the designed septic system for which they bargained and (2) whether the trial court properly found that there was no evidence that the septic system was not working properly.

I

Although the majority states that it is not persuaded by the plaintiffs’ principal claim that the court improperly failed to assign dispositive significance to the pleadings, I am persuaded that the record supports the plaintiffs’ claim and…

2Cases cited5 opinions

  1. Bernstein v. NemeyerSupreme Court of Connecticut · 1990
  2. Rudder v. MAMANASCO LAKE PARK ASS'N, INC.Connecticut Appellate Court · 2006
  3. Strouth v. Pools by Murphy & Sons, Inc.Connecticut Appellate Court · 2003
  4. Solomon v. Connecticut Medical Examining BoardConnecticut Appellate Court · 2004
  5. John Arborio, Inc. v. ScapinSupreme Court of Connecticut · 1936

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API