March v. Butler
South Dakota Supreme Court
1Opinion of the CourtPolley, J.
This action is brought to recover on a contractor’s bond. Defendant Butler took a contract from the state highway commission to do certain road work on a state highway between Hot Springs and .Oelrichs. Butler established a boarding camp to provide board and living quarters for his workmen while carrying on the work provided for in the contract. Plaintiff sold to Butler certain merchandise amounting in value to the sum of $2,257.18, alleged to have been used ¡by the men employed by Butler in carrying on the said work. Upon this amount Butler paid $1,700.50, leaving a balance unpaid of…
2Cases cited3 opinions
- Bricker v. Rollins & JareckiCalifornia Supreme Court · 1918
- J. F. Anderson Lumber Co. v. National Surety Co.South Dakota Supreme Court · 1926
- Clatsop County v. FeldschauOregon Supreme Court · 1921
3Cited by6 opinions
- State Ex Rel. Farmers State Bank v. Ed Cox & SonSouth Dakota Supreme Court · 1965
- Dennis v. EnkeSouth Dakota Supreme Court · 1929
- Finch v. EnkeSouth Dakota Supreme Court · 1929
- Margulies v. OgdieSouth Dakota Supreme Court · 1943
- Finch v. EnkeSouth Dakota Supreme Court · 1929
1 more not listed; retrieve them via the Exa API.