Williams & Works, Inc. v. Springfield Corp.
Michigan Supreme Court
1Opinion of the CourtWilliams, J.
(for reversal). This case concerns the sole question whether oif-site engineering services rendered before the beginning of actual, on- site construction qualify, pursuant to § 9(3) of the Michigan mechanics’ lien law, as "the commencement of said building or buildings, erection, structure or improvement” 1 so as to give priority to mechanics’ liens over a mortgage recorded after the provision of such services but prior to the beginning of any visible, on-site construction. 2
Long established Michigan precedent 3 in line with that in most American jurisdictions 4 requires a visible, on-site…
2Cases cited15 opinions
- Bankers Trust Co. v. El Paso Pre-Cast Co.Supreme Court of Colorado · 1977
- Wallich Lumber Co. v. GoldsMichigan Supreme Court · 1965
- Reuben E. Johnson Co. v. PhelpsSupreme Court of Minnesota · 1968
- Rupp v. Earl H. Cline & Sons, Inc.Court of Appeals of Maryland · 1963
- M. E. Kraft Excavating & Grading Co. v. Barac Construction Co.Supreme Court of Minnesota · 1968
10 more not listed; retrieve them via the Exa API.
3Cited by17 opinions
- MICHIGAN Ex Rel WAYNE COUNTY PROSECUTOR v. BENNISMichigan Supreme Court · 1994
- Michael's Construction, Inc. v. American National BankWyoming Supreme Court · 2012
- Je Dunn Northwest, Inc. v. Corus Const. VentureNevada Supreme Court · 2011
- M D Marinich, Inc v. Michigan National BankMichigan Court of Appeals · 1992
- Durant Construction, Inc v. GourleyMichigan Court of Appeals · 1983
12 more not listed; retrieve them via the Exa API.