George J. Grant Construction Co. v. United States
United States Court of Claims
1Opinion of the CourtMadden, Judge
The plaintiffs, as joint venturers, made a contract with the Government to construct for it three hemp mills at three separate places in Minnesota. The contract price was a lump sum of $301,800, plus unit prices to be paid for work not included in the base bid. The contract was executed on behalf of the Government through the Commodity Credit Corporation, acting on behalf of the Defense Plant Corporation. Both were agencies of the Government.
The contract was dated May 15, 1943. It provided that work should commence V days after the date of the contract, and be completed within 160 calendar…
2Cases cited3 opinions
- United States v. WunderlichSupreme Court of the United States · 1951
- United States v. MoormanSupreme Court of the United States · 1950
- United States v. AmesU.S. Circuit Court for the District of Massachusetts · 1845
3Cited by13 opinions
- Commerce International Company, Inc. v. The United StatesUnited States Court of Claims · 1964
- Law v. United StatesUnited States Court of Claims · 1971
- Buckley & Co., Inc. v. StateNew Jersey Superior Court Appellate Division · 1975
- Commerce International Co. v. United StatesUnited States Court of Claims · 1964
- Aktiebolaget Bofors v. United StatesUnited States Court of Claims · 1957
8 more not listed; retrieve them via the Exa API.