Line Construction Co. v. United States
United States Court of Claims
1Opinion of the CourtJones, Chief Justice
This is a suit for material furnished and work performed under a contract that was canceled before completion.
On April 29, 1942, plaintiff entered into a contract with defendant through the Corps of Engineers of the War Department to install an electric distribution system at the air base, Syracuse, New York. The contract work consisted of removal of existing poles, installing transformers, street lighting equipment, aerial and underground cables, and the reconditioning and reinstalling of existing equipment. It was necessary to install approximately 1,000 poles, including the removing and…
2Cited by9 opinions
- John Reiner & Company, Individually and to the Use of Kurz & Root Company (Incorporated) v. The United StatesUnited States Court of Claims · 1963
- Neil a Goldwasser, Doing Business as Century Offset Company v. The United StatesUnited States Court of Claims · 1963
- Allied Contractors, Inc. v. United StatesUnited States Court of Claims · 1954
- Salsbury Industries v. United StatesUnited States Court of Claims · 1989
- Hadden v. United StatesUnited States Court of Claims · 1955
4 more not listed; retrieve them via the Exa API.