Reif v. Smith
South Dakota Supreme Court
1Opinion of the Court
MORGAN, Justice.
This action was commenced to foreclose a mechanic’s lien for material and labor expended by the contractor (Reif) * in the construction of a residence for David and Patricia Smith (Smiths). Smiths counterclaimed for damages alleging failure to complete the house in a workmanlike manner. The trial court found that Reif had substantially completed the contract and allowed them approximately $6500 on their claim, the equivalent of the balance due on the contract. It further found that Smiths were entitled to approximately $20,850 for cost of completion of the work, correcting…
2Cases cited8 opinions
- Dittmer v. NoklebergNorth Dakota Supreme Court · 1974
- Northern Farm Supply, Inc. v. SprecherSouth Dakota Supreme Court · 1981
- Hulst v. Benevolent Hall Ass'nSouth Dakota Supreme Court · 1896
- Eggers v. LusterWashington Supreme Court · 1948
- Van Den Hoek v. BradwischSouth Dakota Supreme Court · 1978
3 more not listed; retrieve them via the Exa API.
3Cited by13 opinions
- Rosebud Sioux Tribe v. A & P Steel, Inc.Court of Appeals for the Eighth Circuit · 1989
- Dougherty v. BeckmanSouth Dakota Supreme Court · 1984
- Subsurfco, Inc. v. B-Y Water DistrictSouth Dakota Supreme Court · 1983
- Bunkers v. JacobsonSouth Dakota Supreme Court · 2002
- Mooney's, Inc. v. South Dakota Department of TransportationSouth Dakota Supreme Court · 1992