James R. French v. Jinright & Ryan, P.C. Architects
Court of Appeals for the Eleventh Circuit
1Opinion of the Court
RONEY, Circuit Judge:
This is a contractor’s suit against an architect for damages due to construction delays caused by the architect. The district court granted a summary judgment for the defendant architect on the ground that a prior arbitration proceeding effec tively barred the litigation of these claims because they had been litigated in the arbitration proceedings and the plaintiff had received through arbitration some satisfaction for the damages claimed. The Georgia law prohibits continued litigation of inconsistent remedies after satisfaction has been obtained. Because we cannot tell…
2Cases cited13 opinions
- Parklane Hosiery Co. v. ShoreSupreme Court of the United States · 1979
- Allen Deweese v. Town of Palm Beach, Etc., Joseph Terlizzese, Etc., and George MathewsCourt of Appeals for the Eleventh Circuit · 1982
- Robert C. Stovall, Jr. v. Price Waterhouse Co.Court of Appeals for the Fifth Circuit · 1981
- Martha Collins v. Seaboard Coastline Railroad CompanyCourt of Appeals for the Eleventh Circuit · 1982
- McLendon Bros. v. FinchCourt of Appeals of Georgia · 1907
8 more not listed; retrieve them via the Exa API.
3Cited by7 opinions
- Carris v. John R. Thomas & Associates, P.C.Supreme Court of Oklahoma · 1995
- TLT Construction Corp. v. A. Anthony Tappe & Associates, Inc.Massachusetts Appeals Court · 1999
- Wellons, Inc., a Corporation v. T.E. Ibberson Company and Ibberson Engineering, Inc., Formerly Known as Kibcor Engineering, Inc., CorporationsCourt of Appeals for the Eighth Circuit · 1989
- Meldeau International Inc. v. Goodyear Tire & Rubber Co.District Court, S.D. Florida · 1990
- Carris v. John R. Thomas & Associates, P.C.Supreme Court of Oklahoma · 1995
2 more not listed; retrieve them via the Exa API.