Hall v. Harris
Appellate Court of Illinois
1Opinion of the CourtJustice O’Connor
Plaintiff brought suit against the defendant to recover a balance of the contract price for constructing a garage. The amount he claimed was $176. The jury returned a verdict in plaintiff’s favor for $156, judgment was entered on the verdict and the defendant appeals.
Plaintiff’s evidence tends to show that he entered into an oral agreement with the defendant to construct a garage for her for $195; that he proceeded to construct the garage and was required to do extra work amounting to $55, making a total of $250, and that he had been paid $74 on account, leaving a balance due him of $176.…
2Cases cited2 opinions
- Gilmore v. CourtneyIllinois Supreme Court · 1895
- Brennan v. William P. McEvoy & Co.Appellate Court of Illinois · 1915
3Cited by7 opinions
- Northwest Millwork Co. v. KomperdaAppellate Court of Illinois · 2003
- National Wrecking Co. v. Midwest Terminal Corp.Appellate Court of Illinois · 1992
- Abbott Electrical Construction Co. v. LadinAppellate Court of Illinois · 1986
- Weather-Tite, Inc. v. University of St. FrancisAppellate Court of Illinois · 2008
- Northwest Millwork Co. v. KomperdaAppellate Court of Illinois · 2003
2 more not listed; retrieve them via the Exa API.