Northwest Millwork Co. v. Komperda
Appellate Court of Illinois
1Opinion of the CourtJustice McLAREN
Third-party plaintiff, Lipowski & Associates, Inc. (Lipowski), appeals from the dismissal of its action to foreclose on a mechanic’s lien and to recover for breach of contract. On appeal, Lipowski argues that its failure to submit a sworn contractor’s statement does not preclude it from pursuing a breach of contract action. We reverse and remand.
This litigation arises out of the construction of improvements to the home of Casimir J. Komperda and Dawn M. Komperda. The Komperdas hired Lipowski to provide architectural and construction management services on the project. Plaintiff, Northwest…
2Cases cited14 opinions
- R.W. Dunteman Co. v. C/G Enterprises Inc.Illinois Supreme Court · 1998
- Carroll v. PaddockIllinois Supreme Court · 2002
- People v. McKayAppellate Court of Illinois · 1996
- Avakian v. ChulengarianAppellate Court of Illinois · 2002
- Westcon/Dillingham Microtunneling v. Walsh Construction Co.Appellate Court of Illinois · 2001
9 more not listed; retrieve them via the Exa API.
3Cited by1 opinion
- Northwest Millwork Co. v. KomperdaAppellate Court of Illinois · 2003