Huzzy v. Culbert Construction Co.
Court of Appeals of Washington
1Opinion of the CourtJames, J.
Defendant Culbert Construction Co., Inc., contracted to build a house for plaintiff, John P. Huzzy. Without prior notice or demand Huzzy unilaterally terminated the contract, employed another contractor to complete construction, and instituted this action for damages. Huzzy procured writs of garnishment and impounded Culbert’s bank accounts.
Huzzy’s complaint alleges that Culbert breached the contract and “is guilty of having abandoned [its] obligations under the contract, including abandoning further work or building at the site.” He contends that Culbert breached the contract by its shoddy…
2Cases cited11 opinions
- Ferree v. Doric Co.Washington Supreme Court · 1963
- Reynolds Metals Co. v. Electric Smith Construction & Equipment Co.Court of Appeals of Washington · 1971
- McGarvey v. City of SeattleWashington Supreme Court · 1963
- Dunseath v. HallauerWashington Supreme Court · 1953
- Maib v. Maryland Casualty Co.Washington Supreme Court · 1943
6 more not listed; retrieve them via the Exa API.
3Cited by19 opinions
- Hagemann v. WorthCourt of Appeals of Washington · 1989
- Reid Sand & Gravel, Inc. v. Bellevue PropertiesCourt of Appeals of Washington · 1972
- Wagner Development, Inc. v. Fidelity & Deposit Co.Court of Appeals of Washington · 1999
- Van Horn v. Van De Wol, Inc.Court of Appeals of Washington · 1972
- Tilly v. John DoeCourt of Appeals of Washington · 1987
14 more not listed; retrieve them via the Exa API.