Defendants bring this motion before the court on the basis that plaintiff is in violation of a term contained in a construction contract executed between the parties on August 21, 1967, said term being one requiring the submission of disputes between the parties to arbitration as a condition precedent to resort to “any right of legal action that either party may have against the other. ’ ’

Construction of a building was commenced by plaintiff on or about August 21, 1967, and on or about October 19, 1967, one of the walls of said building was destroyed, allegedly through no fault of plaintiff.

Pl…

2Cases cited2 opinions

  1. In re the Arbitration between New York Central Railroad & Erie RailroadNew York Supreme Court · 1961
  2. United States v. MooreDistrict Court, D. New Hampshire · 1882

3Cited by4 opinions

  1. Frederick Contractors, Inc. v. Bel Pre Medical Center, Inc.Court of Appeals of Maryland · 1975
  2. City of Cottonwood v. James L. Fann Contracting, Inc.Court of Appeals of Arizona · 1994
  3. Gannett Fleming, Inc. v. Corman Const.Court of Special Appeals of Maryland · 2019
  4. Williams v. Farmers Ins. ExchangeOhio Court of Appeals · 1990

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API