Legal Opinion

Morello v. Levakis

Massachusetts Supreme Judicial Court

Decided February 24, 1936PublishedCited by 22 opinions

1Opinion of the CourtQua, J.

The plaintiff, a building contractor, brings this action against the owner of a brick building located on Seventh Street, in Springfield, to recover a balance alleged to be due to the plaintiff on account of a written contract between the parties under which the plaintiff has added a second story to the defendant’s building.

The trial judge has refused to find for the plaintiff on *451the written contract, presumably because of certain deficiencies in performance. Bowen v. Kimbell, 203 Mass. 364. Searls v. Loring, 275 Mass. 403. He has, however, after deducting $85 for the deficiencies, found for…

2Cases cited21 opinions

  1. Bowen v. KimbellMassachusetts Supreme Judicial Court · 1909
  2. Handy v. BlissMassachusetts Supreme Judicial Court · 1910
  3. Nowel v. Equitable Trust Co.Massachusetts Supreme Judicial Court · 1924
  4. Salem Trust Co. v. DeeryMassachusetts Supreme Judicial Court · 1935
  5. O'Brien v. SheaMassachusetts Supreme Judicial Court · 1911

16 more not listed; retrieve them via the Exa API.

3Cited by22 opinions

  1. J. A. Sullivan Corp. v. CommonwealthMassachusetts Supreme Judicial Court · 1986
  2. Nussenbaum v. Chambers & Chambers Inc.Massachusetts Supreme Judicial Court · 1948
  3. Andre v. MaguireMassachusetts Supreme Judicial Court · 1940
  4. Hart v. BellSupreme Court of Minnesota · 1946
  5. Gleason v. MannMassachusetts Supreme Judicial Court · 1942

17 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API