Mall, Inc. v. City of Seattle
Washington Supreme Court
1Opinion of the CourtGoodloe, J.
Appellant Mall, Inc., applied for permission to construct a 35-story building on the site of the Bar-tell Building in downtown Seattle. Its application was denied by the Seattle Department of Construction and Land Use (DCLU) because the building's proposed total floor area greatly exceeded the maximum allowed under the Seattle Municipal Code. The Seattle Hearing Examiner and trial court upheld the DCLU's interpretation. Mall contends on appeal that its fee interest in the land underlying Westlake Avenue, which lies adjacent to the site, should be included in the computation of its lot area,…
2Cases cited40 opinions
- Sorenson v. City of BellinghamWashington Supreme Court · 1972
- Hama Hama Co. v. Shorelines Hearings BoardWashington Supreme Court · 1975
- In Re the Personal Restraint of MyersWashington Supreme Court · 1986
- Alderwood Water District v. Pope & Talbot, Inc.Washington Supreme Court · 1963
- Morin v. JohnsonWashington Supreme Court · 1956
35 more not listed; retrieve them via the Exa API.
3Cited by36 opinions
- Phillips v. City of SeattleWashington Supreme Court · 1989
- Washington Water Power Co. v. Graybar Electric Co.Washington Supreme Court · 1989
- Hart v. DEPT. OF SOCIAL AND HEALTH SERVS.Washington Supreme Court · 1988
- Sleasman v. City of LaceyWashington Supreme Court · 2007
- Sleasman v. City of LaceyWashington Supreme Court · 2007
31 more not listed; retrieve them via the Exa API.