Cutler Construction, Inc. v. Omni Builders, Inc.
Massachusetts District Court, Appellate Division
1Opinion of the CourtDoyle, P.J.
This is an action in contract in which a finding was entered for the plaintiffs. The sole issue for review is whether the trial court properly dismissed the defendants’ request for report as untimely pursuant to Dist./Mun. Cts. R. Civ. P., Rule 64(c)(l)(i).
Judgment was entered for the plaintiff herein on June 24,1983. Six weeks later, the defendants filed a Dist./Mun. Cts. R. Civ. P., Rule 60 motion for relief from judgment in which the defendants requested a new trial for the purpose of introducing additional testimony by an expert witness. On October 6,1983, the trial justice allowed the…
2Cases cited12 opinions
- International Controls Corp. v. Robert L. Vesco, and Vesco & Co., Inc.Court of Appeals for the Second Circuit · 1977
- Parrell v. KeenanMassachusetts Supreme Judicial Court · 1983
- Locke v. SlaterMassachusetts Supreme Judicial Court · 1982
- Albano v. Bonanza International Development Co.Massachusetts Appeals Court · 1977
- Politano v. Board of SelectmenMassachusetts Appeals Court · 1981
7 more not listed; retrieve them via the Exa API.
3Cited by1 opinion
- Kirby v. Miami Systems Corp.Massachusetts District Court, Appellate Division · 1999