Findlen v. Winchendon Housing Authority
Massachusetts Appeals Court
1Opinion of the Court
Although the construction contract between the Winchendon Housing Authority (Authority), as owner, and Fred J. Findlen & Sons (Findlen), as general contractor, contained a sweeping provision disclaiming any liability by the owner for job delays, Findlen obtained, on account of delay damages, a judgment for $29,056.82, the amount it paid in a separate action to one of its subcontractors, plus $2,500 in attorney’s fees. We conclude that through a series of memoranda and letters the owner modified the scope of the original provision exculpating it from a duty to pay delay damages and we affirm…
2Cases cited15 opinions
- Charles I. Hosmer, Inc. v. CommonwealthMassachusetts Supreme Judicial Court · 1939
- M. L. Shalloo, Inc. v. Ricciardi & Sons Construction, Inc.Massachusetts Supreme Judicial Court · 1965
- Coleman Bros. v. CommonwealthMassachusetts Supreme Judicial Court · 1940
- Chas. T. Main, Inc. v. Massachusetts Turnpike AuthorityMassachusetts Supreme Judicial Court · 1964
- A. Leo Nash Steel Corp. v. Southern New England Steel Erection Co.Massachusetts Appeals Court · 1980
10 more not listed; retrieve them via the Exa API.
3Cited by2 opinions
- Bonacorso Construction Corp. v. CommonwealthMassachusetts Appeals Court · 1996
- XL Specialty Insurance v. Massachusetts Highway DepartmentMassachusetts Superior Court · 2013