Legal Opinion

Nova group/tutor-saliba v. United States

United States Court of Federal Claims

Decided March 16, 2016No. 15-885CPublishedCited by 5 opinions

1Opinion of the Court

Rule 12(b)(6); Motion to Dismiss; Constructive Change; Timely Written Notice; FAR 52.243-4; Actual Notice; Extenuating Circumstances Excusing Timely Written Notice.

OPINION AND ORDER

WILLIAMS, Judge.

This Contract Disputes Act case comes before the Court on Defendant’s motion to dismiss for failure to state a claim upon which relief can be granted. Plaintiff, a joint venture, entered into a contract with the Naval Facilities Engineering Command (“NAVFAC”), a component of the United States Navy, to design and build a pier at the Puget Sound Navy Shipyard in Bremerton, Washington. Plaintiff…

2Cases cited11 opinions

  1. Ashcroft v. IqbalSupreme Court of the United States · 2009
  2. Bell Atlantic Corp. v. TwomblySupreme Court of the United States · 2007
  3. Daniel A. Lindsay v. United StatesCourt of Appeals for the Federal Circuit · 2002
  4. bell/heery v. United StatesCourt of Appeals for the Federal Circuit · 2014
  5. K-Con Building Systems, Inc. v. United StatesCourt of Appeals for the Federal Circuit · 2015

6 more not listed; retrieve them via the Exa API.

3Cited by5 opinions

  1. DISTRICT OF COLUMBIA v. DISTRICT OF COLUMBIA CONTRACT APPEALS BOARD, and PRINCE CONSTRUCTION CO., INC., and W.M. SCHLOSSER CONSTRUCTION CO., INCDistrict of Columbia Court of Appeals · 2016
  2. Nova group/tutor-saliba v. United StatesUnited States Court of Federal Claims · 2016
  3. Cb&i Areva Mox Services, LLC v. United StatesUnited States Court of Federal Claims · 2018
  4. Cb&i Areva Mox Services, LLC v. United StatesUnited States Court of Federal Claims · 2018
  5. Nova group/tutor-saliba v. United StatesUnited States Court of Federal Claims · 2022

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API