LAKE, Chief Justice.

The question presented for review in this case is whether a new building constructed by an electric customer remained part of an existing, adjoining “premises” requiring continued electric service from its original supplier, or whether such building became a “premises initially requiring electric service” under the terms of the Electric Territorial Assignment Act of 1965 (the “Electric Act”), and thus was eligible to receive electric service from a new supplier, Carteret-Craven Electric Membership Corporation. See N.C.G.S. § 160A-332(a)(3) (2001). The Court of Appeals…

2Cases cited7 opinions

  1. State Ex Rel. Utilities Commission v. EdmistenSupreme Court of North Carolina · 1977
  2. State ex rel. Utilities Commission v. Lumbee River Electric Membership Corp.Supreme Court of North Carolina · 1969
  3. Domestic Electric Service, Inc. v. City of Rocky MountSupreme Court of North Carolina · 1974
  4. Hlasnick v. Federated Mutual InsuranceSupreme Court of North Carolina · 2000
  5. State Ex Rel. Utilities Commission v. Woodstock Electric Membership Corp.Supreme Court of North Carolina · 1970

2 more not listed; retrieve them via the Exa API.

3Cited by1 opinion

  1. In re Town of Smithfield for Approval of Agreement between Electric Suppliers with Carolina Power & Light Co.Court of Appeals of North Carolina · 2013