William Cramp & Sons Ship & Engine Building Co. v. United States
United States Court of Claims
The Reporter’s statement of the case:
1Opinion of the CourtBooth, Judge
This case is again before the court on motion for new trial by both claimants and defendants.
The claimant company, on October 1, 1898, entered into a contract with the defendant to construct the battleship Maine. The claimant was to furnish all the necessary material entering into the vessel except the armor and armament and to complete the same within 32 months from the date of the contract, viz, June 1, 1901. The defendants agreed to furnish the armor specified in clause 3 of the contract “ within the times and in the order required to carry on the work properly.” The claimant subsequent to…
2Cases cited6 opinions
- United States v. BehanSupreme Court of the United States · 1884
- Myerle v. United StatesUnited States Court of Claims · 1897
- United States v. William Cramp & Sons Ship & Engine Building Co.Supreme Court of the United States · 1907
- District of Columbia v. Camden Iron WorksSupreme Court of the United States · 1901
- Weeks v. . LittleNew York Court of Appeals · 1882
1 more not listed; retrieve them via the Exa API.
3Cited by6 opinions
- Harvey Ward Locke v. United StatesUnited States Court of Claims · 1960
- James Stewart & Co. v. United StatesUnited States Court of Claims · 1946
- Tester Corp. v. United StatesUnited States Court of Claims · 1982
- Armour of America v. United StatesUnited States Court of Federal Claims · 2011
- Globe Works v. United StatesUnited States Court of Claims · 1918
1 more not listed; retrieve them via the Exa API.