Grier-Lowrance Construction Co. v. Winston-Salem Journal Co.
Supreme Court of North Carolina
1Opinion of the CourtBeogdeN, J.
Can a contractor sue the owner and recover the contract price for labor and material furnished such owner by a subcontractor or materialman; and, if so, under what circumstances ?
In Hardware Co. v. Schools, 151 N. C., 507, 66 S. E., 583, this Court said: “Even a cursory perusal of our statute (Revisal, ch. 48) will make it plainly appear that a subcontractor or a person who furnishes materials for the construction of the building has no claim against the owner apart from the claim he acquires by virtue of his lien after notice to the owner and before he settles with the contractor. The…
2Cases cited9 opinions
- Charlotte Pipe & Foundry Co. v. Southern Aluminum Co.Supreme Court of North Carolina · 1916
- Morganton Hardware Co. v. Morganton Graded SchoolsSupreme Court of North Carolina · 1909
- King v. . ElliottSupreme Court of North Carolina · 1929
- G. W. Jefferson & Bros. v. BryantSupreme Court of North Carolina · 1913
- Norfolk Building Supplies Co. v. Elizabeth City Hospital Co.Supreme Court of North Carolina · 1918
4 more not listed; retrieve them via the Exa API.
3Cited by7 opinions
- Schnepp v. . RichardsonSupreme Court of North Carolina · 1942
- Economy Pumps, Inc. v. F. W. Woolworth Co.Supreme Court of North Carolina · 1941
- Boykin v. . LoganSupreme Court of North Carolina · 1932
- Building Corporation v. . JonesSupreme Court of North Carolina · 1917
- Huske Hardware House v. PercivalSupreme Court of North Carolina · 1932