Master Builders Ass'n v. Carson
Supreme Court of Kansas
1Opinion of the Court
The opinion of the court was delivered by
Smith, J.:
The action was brought to collect the amount of money which defendant had agreed to pay plaintiff in case defendant should be awarded the contract to build a certain schoolhouse. A demurrer to the petition was sustained. Plaintiff appeals.
The facts are that defendant entered into a contract with several other contractors who were about to bid for the contract to'build a schoolhouse in Cherryvale, and with plaintiff association. The pertinent part of the contract was as follows:
“We, the undersigned, being general building contractors, bidding…
2Cases cited2 opinions
- Kentucky Association Highway Contractors v. WilliamsCourt of Appeals of Kentucky (pre-1976) · 1926
- Gard v. Estate of HolmesSupreme Court of Kansas · 1931
3Cited by4 opinions
- Coleman v. Safeway Stores, Inc.Supreme Court of Kansas · 1988
- Zion's Service Corporation v. DanielsonUtah Supreme Court · 1961
- Constructors Ass'n of Western Pennsylvania v. SeedsSuperior Court of Pennsylvania · 1940
- Griffiths & Sprague Stevedoring Co. v. Waterfront Employers Ass'n of Pacific CoastCourt of Appeals for the Ninth Circuit · 1947