American Public Gas Association v. Federal Power Commission, American Public Power Association, Intervenor
Court of Appeals for the D.C. Circuit
1Opinion of the Court
BRODERICK, District Judge:
On October 10, 1974, the Federal Power Commission (Commission) raised from 7% to 9% the rate of interest to be paid on refunds ordered by the Commission in connection with any rates and charges which it found not justified. The Commission’s Order limits the 9% rate of interest to refunds ordered by the Commission in cases where the rate filings were made on or after Octo ber 10, 1974, the date of the Commission’s Order. Petitioners, the American Public Gas Association, the Indiana Municipal Electric Association, the Ohio Municipal Electric Association, the Indiana…
2Cases cited11 opinions
- Federal Power Commission v. Hope Natural Gas Co.Supreme Court of the United States · 1944
- Permian Basin Area Rate CasesSupreme Court of the United States · 1968
- City of Chicago, Illinois v. Federal Power Commission, Pipeline Production Group, IntervenorsCourt of Appeals for the D.C. Circuit · 1972
- Federal Power Commission v. Tennessee Gas Transmission Co.Supreme Court of the United States · 1962
- Pacific Gas & Electric Co. v. Federal Power CommissionCourt of Appeals for the D.C. Circuit · 1974
6 more not listed; retrieve them via the Exa API.
3Cited by12 opinions
- Princemont Construction Corp. v. A. D. SmithCourt of Appeals for the D.C. Circuit · 1970
- Gulf Oil Corp. v. Federal Power CommissionCourt of Appeals for the Third Circuit · 1977
- Public Systems v. Federal Energy Regulatory CommissionCourt of Appeals for the D.C. Circuit · 1979
- United Gas Pipe Line Company v. Federal Energy Regulatory CommissionCourt of Appeals for the Fifth Circuit · 1981
- Federal Energy Regulatory Commission v. Triton Oil and Gas CorporationCourt of Appeals for the D.C. Circuit · 1984
7 more not listed; retrieve them via the Exa API.