J. J. Kelly Co. v. United States

United States Court of Claims

Decided January 6, 1947No. 46032PublishedCited by 10 opinions

1Opinion of the Court

JONES, Judge.

Plaintiff on November 2, 1942, contracted to construct for the defendant a decontamination building in the Navy Yard at Philadelphia, Pennsylvania.

Notice to proceed was given December 10, 1942, thus fixing February 8, 1943, as the date for completion of the work.

The work was completed May 1, 1943, except for some items which were taken over by the Government. This was 82 days later than the contract date for completion.

The contracting officer advised plaintiff in writing that the delay was due to unforeseeable causes beyond plaintiff’s control and he, therefore, extended for a…

2Cases cited4 opinions

  1. Horowitz v. United StatesSupreme Court of the United States · 1925
  2. United States v. Howard P. Foley Co.Supreme Court of the United States · 1946
  3. J. F. Barbour & Sons v. United StatesUnited States Court of Claims · 1945
  4. Harwood-Nebel Construction Co. v. United StatesUnited States Court of Claims · 1945

3Cited by10 opinions

  1. Griffith Co. v. San Diego College for WomenCalifornia Supreme Court · 1955
  2. Kehm Corp. v. United StatesUnited States Court of Claims · 1950
  3. Chalender v. United StatesUnited States Court of Claims · 1954
  4. Jacob Lichter and Jennie L. Lichter, Partners, Doing Business as Southern Fireproofing Company v. Mellon-Stuart CompanyCourt of Appeals for the Third Circuit · 1962
  5. Chalender v. United StatesUnited States Court of Claims · 1954

5 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API