LITTLETON, Judge.

Plaintiff and defendant, acting through the Federal Works Agency, entered into a contract March 25, 1942, in which plaintiff agreed for the lump sum of $266,722.22 to furnish the necessary materials and labor, and to perform all the work necessary for the construction of a community hospital at a Defense Housing Project at Radford, Va. The contract- provided for completion of the building within 210 calendar days after notice to proceed, or by November 9, 1942.

Recovery of damages of $30,000 is sought on the ground that defendant, through actions of the contracting officer and…

2Cases cited1 opinion

  1. J. F. Barbour & Sons v. United StatesUnited States Court of Claims · 1944

3Cited by9 opinions

  1. Clemmer Const. Co. v. United StatesUnited States Court of Claims · 1947
  2. Froemming Bros., Inc., of Texas v. United StatesUnited States Court of Claims · 1947
  3. Klamath Irrigation District v. United StatesUnited States Court of Federal Claims · 2007
  4. J. J. Kelly Co. v. United StatesUnited States Court of Claims · 1947
  5. Bruno New York Industries Corp. v. The United StatesUnited States Court of Claims · 1965

4 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API