NIPPON HODO COMPANY v. United States
United States Court of Claims
1Opinion of the Court
MADDEN, Judge.
The plaintiff, a Japanese corporation, made a contract with the United States on June 28, 1950, for the construction of a runway, taxiways and aprons at an air base in Japan. The contract price was some $744,000. Upon the completion of the work, the plaintiff was paid the amount admittedly due it, and executed a release, from which release, however, five specific items of claim were excepted.
One of the five excepted items was a claim for “increased cost required for construction of the base course in a manner different from plans and specifications.” It is that claim which is…
2Cases cited1 opinion
- L. W. Packard & Co. v. United StatesUnited States Court of Claims · 1928
3Cited by17 opinions
- J. G. Watts Construction Co. v. United StatesUnited States Court of Claims · 1963
- H.L.C. & Associates Construction Company, Inc. v. The United StatesUnited States Court of Claims · 1966
- Charles Merrill Mount v. Book-Of-The-Month Club, Inc.Court of Appeals for the Second Circuit · 1977
- A & K Plumbing & Mechanical, Inc. v. United StatesUnited States Court of Claims · 1983
- Julius Goldman's Egg City v. United StatesUnited States Court of Claims · 1977
12 more not listed; retrieve them via the Exa API.