Abatement Contracting Corp. v. United States
United States Court of Federal Claims
1Opinion of the Court
OPINION
ME ROW, Senior Judge.
On June 11, 1993, the United States Naval Academy solicited bids for a “Requirements Contract for Asbestos Removal and Insulation Installation, U.S. Naval Academy and U.S. Naval Station, Annapolis, Maryland” with an estimated cost of between $500,000.00 and $1,000,000.00. PLApp. 001, 003-009. By Amendment/Modification No. 0001 dated June 14,1993, the Solicitation was amended from a requirements to an indefinite quantity contract. PLApp. 010-014. The indefinite quantity contract (“Contract”) made it clear that it was not a fixed-price contract, that there were no…
2Cases cited34 opinions
- Anderson v. Liberty Lobby, Inc.Supreme Court of the United States · 1986
- Mingus Constructors, Inc. v. The United StatesCourt of Appeals for the Federal Circuit · 1987
- Am-Pro Protective Agency, Inc. v. United StatesCourt of Appeals for the Federal Circuit · 2002
- Community Heating & Plumbing Company, Inc. v. Admiral Frank B. Kelso, Ii, Acting Secretary of the NavyCourt of Appeals for the Federal Circuit · 1993
- Monon Corporation and Rosby Corporation, Plaintiffs-Cross v. Stoughton Trailers, Inc.Court of Appeals for the Federal Circuit · 2001
29 more not listed; retrieve them via the Exa API.
3Cited by7 opinions
- A & D Fire Protection, Inc. v. United StatesUnited States Court of Federal Claims · 2006
- Admiral Financial Corp. v. United StatesUnited States Court of Federal Claims · 2002
- Unfoldment, Inc. v. District of Columbia Contract Appeals BoardDistrict of Columbia Court of Appeals · 2006
- Cygnus Corp. v. United StatesUnited States Court of Federal Claims · 2004
- J.L. Simmons Co. v. United StatesUnited States Court of Federal Claims · 2004
2 more not listed; retrieve them via the Exa API.