Feldman v. Davey Development Co.
Massachusetts Supreme Judicial Court
1Opinion of the Court
Order dismissing report affirmed. This is an action of contract to recover from the defendant for building materials ordered by one Soper. The plaintiffs contend that the defendant was an undisclosed principal of Soper. The judge found that the plaintiffs “received a note from one Herbert Soper and his son in the amount of $4,743.38 which amount is the amount claimed in the plaintiffs’ declaration . . . and I am therefore finding that the plaintiffs extended credit to said Soper and not [to] the defendant.” A report to the Appellate Division was dismissed and the plaintiffs appealed. The…
2Cases cited1 opinion
- Vieira v. BalsamoMassachusetts Supreme Judicial Court · 1951
3Cited by7 opinions
- Lane v. SmithMassachusetts District Court, Appellate Division · 1975
- Ryan v. VeraMassachusetts District Court, Appellate Division · 1984
- Goldman v. GirouxMassachusetts District Court, Appellate Division · 1985
- Goober v. WayneMassachusetts District Court, Appellate Division · 1967
- Levenson v. BertoletMassachusetts District Court, Appellate Division · 1976
2 more not listed; retrieve them via the Exa API.