Eagle v. Redmond Building Corp.
Missouri Court of Appeals
1Opinion of the Court
LAURA DENVIR STITH, Presiding Judge.
Robert and Sandra Eagle contracted with Redmond Building Corporation for the construction of a new house. The Eagles were unsatisfied with the house as completed and filed a petition alleging that Redmond breached its contract with them by falling to construct the house in a workmanlike manner. They requested damages for cost of repair and for attorney’s fees, as permitted by their contract, and submitted evidence *292that they had spent $11,177.00 for repairs and $13,384.50 for attorney’s fees.
On appeal, Redmond argues that this evidence was inadequate to…
2Cases cited10 opinions
- State Ex Rel. Missouri Highway & Transportation Commission v. Jim Lynch Toyota, Inc.Missouri Court of Appeals · 1992
- Howard Construction Co. v. Teddy Woods Construction Co.Missouri Court of Appeals · 1991
- Wright v. Fox-Stanley Photo Products, Inc.Missouri Court of Appeals · 1982
- Sydnor v. Director of RevenueMissouri Court of Appeals · 1994
- Pruitt v. Community Tire Co.Missouri Court of Appeals · 1984
5 more not listed; retrieve them via the Exa API.
3Cited by3 opinions
- Eagle Ex Rel. Estate of Eagle v. RedmondMissouri Court of Appeals · 2002
- Dick v. Children's Mercy HospitalMissouri Court of Appeals · 2004
- Meyer v. PurcellMissouri Court of Appeals · 2013