Legal Opinion

Stoughton Lumber Co. v. Ogren

Massachusetts Supreme Judicial Court

Decided June 23, 1931PublishedCited by 1 opinion

1Opinion of the CourtCarroll, J.

In this action the plaintiff seeks to recover $1,014.60 for materials furnished in the construction of a house for the defendant. In March, 1926, one Lepine made a contract in writing with the defendant to build a house for the sum of $3,600, to be paid $300 “when foundation in,” $1,000 “when framed, boarded and roof covered,” $700 “when outside is finished and rough plumbing and wiring,” $700 “when house is ready for finish,” $300 “when standing finish is on,” and $600 “when house is finished and bills are paid.” Lepine applied to the plaintiff to supply the lumber and certain materials. The…

2Cases cited5 opinions

  1. O'Connell v. RootMassachusetts Supreme Judicial Court · 1926
  2. Russell v. BarryMassachusetts Supreme Judicial Court · 1874
  3. Somers v. ThayerMassachusetts Supreme Judicial Court · 1874
  4. Dolben v. KaufmanMassachusetts Supreme Judicial Court · 1930
  5. Rothenberg v. Newton Mortgage Corp.Massachusetts Supreme Judicial Court · 1930

3Cited by1 opinion

  1. Kurland v. Massachusetts Amusement Corp.Massachusetts Supreme Judicial Court · 1940