1Opinion of the CourtDupont, C. J.
In this action, Morganti, Incorporated (Morganti), applied for an order confirming an arbitration award and Boehringer Ingelheim Pharmaceuticals, Inc. (BIP), in a separate application, moved to vacate that same award.
On August 23,1983, the parties entered into a written agreement wherein Morganti agreed, as a general contractor, to construct and renovate the research and *69development facilities owned by BIP at its facility in Ridgefield. At the conclusion of the project on August 8, 1986, Morganti filed a demand for arbitration pursuant to the arbitration clause contained in that contract, §…
2Cases cited12 opinions
- Pandolphe's Auto Parts, Inc. v. Town of ManchesterSupreme Court of Connecticut · 1980
- State v. EllisSupreme Court of Connecticut · 1985
- O & G/O'Connell Joint Venture v. Chase Family Ltd. Partnership No. 3Supreme Court of Connecticut · 1987
- State v. AillonSupreme Court of Connecticut · 1983
- Meyers v. Lakeridge Development Co.Supreme Court of Connecticut · 1977
7 more not listed; retrieve them via the Exa API.
3Cited by10 opinions
- CFM of Connecticut, Inc. v. ChowdhurySupreme Court of Connecticut · 1996
- Carnese v. MiddletonConnecticut Appellate Court · 1992
- Stabenau v. CairelliConnecticut Appellate Court · 1990
- Glinski v. GlinskiConnecticut Appellate Court · 1992
- Greater Bridgeport Transit District v. Amalgamated Transit Union, Local 1336Connecticut Appellate Court · 1992
5 more not listed; retrieve them via the Exa API.